Contract overview
| Contractor Name | Auction | Status |
|---|---|---|
| Gold Fields Australia Pty Limited | Apr-16 | Completed |
Contracted project(s)
- Granny Smith Gas Power Station (EOP101217)
Delivery data
| Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|
| Fixed Delivery | 85,845 | 10,828 | 75,017 |
Contract timing
| Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
|---|---|---|---|---|---|
| 5.94 years | 7.30 years | 22/08/2023 | 7.00 years | Yes | 8.36 years |