Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| EOP101217 | Energy Efficiency | Carbon Credits (Carbon Farming Initiative-Industrial Electricity and Fuel Efficiency) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project improves energy (electricity and fuel) efficiency by modifying, removing or replacing existing energy-consuming equipment, and changing the energy sources or mix of energy sources used by existing energy-consuming equipment. | Fuel switching | n/a | n/a | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| Gold Fields Australia Pty Limited | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 26/05/2015 | 1/06/2016 - 31/05/2023 | n/a | n/a |
Related contract(s)
| Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|---|
| CAC201966 | Completed | Apr-16 | 85,845 | 75,017 |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Western Australia | 6440 | n/a | No mapping files provided |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 101155 | 0 | 0 | 0 |
Notes
22/08/2023 This project was contracted in May-16 and CAC201966 has now been completed.