Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| ERF183695 | Vegetation | Carbon Credits (Carbon Farming Initiative-Plantation Forestry) Methodology Determination 2022
Read the methodology determination |
This project sequesters carbon by establishing and maintaining a new plantation forest for commercial harvesting of wood products. This project sequesters carbon by converting an existing short rotation plantation forest to a long rotation plantation forest for commercial harvesting of wood products. | Establishment of a new plantation forest | n/a | n/a | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| HANCOCK VICTORIAN PLANTATIONS PTY LIMITED | Wen Long Liu |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 8/08/2023 | 31/08/2024 - 30/08/2049 | Permanence period has not commenced yet. The nominated period is 25 years. |
n/a |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Victoria | 3249, 3266, 3302, 3373, 3700, 3701, 3862, 3864, 3870, 3971 | 5A~A/271492W/06689/622; 22A/760796Y/07443/509; 22A/760796Y/07443/509; 23A/391383G/07838/064; Lot 1/822150J/08718/586; Lot 1/831026J/08718/587; 25A/291131T/09678/283; Lot 2/729749Y/11568/530; Lot 1 Sec. C/305522G/10934/830; Lot 1/536385Y/07489/062; 4A Sec. 8/281510R/04305/952; 4B Sec. 8/266218X/09007/833; 4A1 Sec. 8/TP528271L/02982/319; 3A Sec. 8/277451E/09007/831; Lot 1/544411T/10934/828; 6A/822152E/04352/358; Lot 2/611736R/11083/352; 3C Sec. 8/277453A/09007/835; 6A/822152E/04352/358; 46B~A/670125F/10959/759; 46~A/778791K/10959/757; Lot 2/812969V/12073/104; 46A~A/778791K/10959/757; Lot 2/537583C/10963/696; Lot 7/727373F/11614/147; Lot 8/727373F/11614/148; Lot 9A/727373F/11614/149; Lot 9B/727373F/11614/150; Lot 10/727373F/11614/151; 73R/765660Y/11614/154; 74P/765660Y/11614/154; 73F/765660Y/11614/154; 74Q/765660Y/11614/154; 73H/765660Y/11614/154; 73D/765660Y/11614/154; Lot 1/444320R/08248/698; 32D/315730S/08067/207; Lot 1/246327F/08300/177; 73C/296314H/09007/163; 69C/266234A/09007/164; Lot 1/125619S/09007/169; 73K/284276F/09007/165; 69B/296315F/09007/166; Lot 1/233429U/09007/167; 69P/261926V/09007/168; Lot 2/125619S/09007/169; 157F/117564/11730/745; 4A Sec. 1/310653L/09150/526; Sec 1 CA 4 and 5 (part)/169941F/09904/603; Lot 1/TP893342X/07735/157; 22 Sec.3/754443U/05290/836; 22A Sec.3/362100M/05290/837; Lot 1/614939K/11166/361; Lot 1 Sec. 7/354369K/03110/808; Lot 3 Sec. 7/426012F/03973/519; 22 Sec. 14/TP359898D/4418/534; Lot 2/PS725300V/11518/481 The project is in the Wellington, Pyrenees, Colac Otway, Corangamite, Latrobe (Vic.), Towong, Southern Grampians local government areas. |
Project area mapping file (.kml) |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 0 | 0 | 0 | 0 |
Notes
27/05/2024 Variation to the project area areas have been added to the project.
22/07/2024 Variation to the project area areas have been added to the project.
04/02/2025 Variation to the project area areas have been added to the project.
04/04/2025 Variation to the project area - areas have been added to the project.
22/05/2025 Variation to the project area - areas have been added to the project.
11/07/2025 Variation to the project area - areas have been added to the project.
13/08/2025 Variation to the project area areas have been added to the project.
18/08/2025 Variation to the project area areas have been added to the project.
25/08/2025 Variation to the project area areas have been added to the project.
30/09/2025 Variation to the project area areas have been added to the project.
22/07/2024 Variation to the project area areas have been added to the project.
04/02/2025 Variation to the project area areas have been added to the project.
04/04/2025 Variation to the project area - areas have been added to the project.
22/05/2025 Variation to the project area - areas have been added to the project.
11/07/2025 Variation to the project area - areas have been added to the project.
13/08/2025 Variation to the project area areas have been added to the project.
18/08/2025 Variation to the project area areas have been added to the project.
25/08/2025 Variation to the project area areas have been added to the project.
30/09/2025 Variation to the project area areas have been added to the project.