Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| ERF170687 | Waste | Carbon Credits (Carbon Farming Initiative-Electricity Generation from Landfill Gas) Methodology Determination 2021 (Compilation No. 1)
Read the methodology determination |
This project upgrades an existing landfill gas collection system to capture and combust gas generated at the landfill from legacy and non-legacy waste. | Upgraded from an existing landfill gas collection system | n/a | Methane sent to a combustion device or biogas upgrading system calculated using the energy content of landfill gas | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| LMS Energy Pty Ltd | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 20/06/2022 | 1/12/2022 - 30/11/2034 | n/a | n/a |
Related contract(s)
| Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|---|
| CAC518898 | Active | Mar-23 | 58,000 | 0 |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| New South Wales | 2256 | n/a | No mapping files provided |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 69322 | 0 | 0 | 0 |
Notes
21/02/2024 Variation of project method - from the Carbon Credits (Carbon Farming Initiative-Landfill Gas) Methodology Determination 2015 (Compilation No. 1) (F2021C00494) to the Carbon Credits (Carbon Farming Initiative-Electricity Generation from Landfill Gas) Methodology Determination 2021 (F2022C00231).