Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| ERF166066 | Vegetation | Carbon Credits (Carbon Farming Initiative-Plantation Forestry) Methodology Determination 2022
Read the methodology determination |
This project sequesters carbon by establishing and maintaining a new plantation forest for commercial harvesting of wood products and avoiding conversion of a plantation to non-forested land by continuing plantation project activity. | Establishment of a new plantation forest | n/a | n/a | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| WATER CORPORATION | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 20/08/2021 | 15/03/2022 - 14/03/2047 | Permanence period has not commenced yet. The nominated period is 25 years. |
n/a |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Western Australia | 6225, 6390 | 1/P77112/2840/699, 1455/P140079, 164/P301920, 165/P301920, 2038/P140196, 2056/P201675, 2130/P140442, 2317/P134306, 2318/P129307, 2367/P129299, 2368/P129300, 2381/P134307, 2515/P136359, 2516/P134303, 270/P302004, 3655/P134307, 4491/P157574 The project is in the SHIRE OF BODDINGTON, Shire of Boyup Brook local government areas. |
Project area mapping file (.kml) |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 0 | 0 | 0 | 0 |
Notes
30/07/2022 Variation of project method - from Carbon Credits (Carbon Farming Initiative Plantation Forestry) Methodology Determination 2017 (Compilation No. 1) (F2020C00072) to Carbon Credits (Carbon Farming Initiative Plantation Forestry) Methodology Determination 2022 (F2022L00047).
25/05/2023 Variation to the project area - areas have been added to the project.
25/05/2023 Variation to the project area - areas have been added to the project.