Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
ERF132693 | Waste | Carbon Credits (Carbon Farming Initiative-Electricity Generation from Landfill Gas) Methodology Determination 2021 (Compilation No. 1)
Read the methodology determination |
This project upgrades an existing landfill gas collection system to capture and combust gas generated at the landfill from legacy and non-legacy waste. |
Participants
Project Proponent |
---|
LGI Limited |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
11/06/2020 | 24/07/2020 - 23/07/2027 | n/a |
Related contract(s)
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
Australian Capital Territory | 2609 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
367427 | 0 | 0 | 0 |
Notes
03/05/2023 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F021C00494) to Carbon Credits (Carbon Farming Initiative - Electricity Generation from Landfill Gas) Methodology Determination 2021 (F2022C00231).