Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
ERF105101 | Industrial Fugitives | Carbon Credits (Carbon Farming Initiative-Coal Mine Waste Gas) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project is a displacement electricity production project that is installing and operating electricity production devices to capture and combust the methane component of coal mine waste gas from the mine. |
Participants
Project Proponent |
---|
EDL CSM (Qld) Pty Ltd |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
31/10/2016 | 1/01/2018 - 31/12/2024 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC615972 | Lapsed/Terminated | Nov-16 | 857,483 | 0 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
Queensland | 4744 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
0 | 0 | 0 | 0 |
Notes
04/01/2021 This project was contracted in Nov-16 and CAC615972 has now been completed, has lapsed, or has been terminated. See the Carbon abatement contract register for further details.
25/10/2022 This project has been revoked under section 30 of the CFI Rule.
25/10/2022 This project has been revoked under section 30 of the CFI Rule.