Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
ERF105023 | Industrial Fugitives | Carbon Credits (Carbon Farming Initiative-Coal Mine Waste Gas) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project is a new flaring project that is installing and operating new flaring devices to capture and combust the methane component of coal mine waste gas from the mine. |
Participants
Project Proponent |
---|
Our Energy Group Pty Limited |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
8/11/2016 | 9/10/2017 - 8/10/2024 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC838267 | Lapsed/Terminated | Nov-16 | 300,000 | 0 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
New South Wales | 2330 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
0 | 0 | 0 | 0 |
Notes
04/11/2019 This project was contracted in November 2016 and CAC838267 has now been terminated or lapsed.