Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| ERF102020 | Energy Efficiency | Carbon Credits (Carbon Farming Initiative-Commercial and Public Lighting) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project is a lighting upgrade project that is modifying, replacing and supplementing the lighting system of various types of serviced areas. |
|
n/a | n/a | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| National Carbon Bank of Australia Pty Ltd | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 13/10/2015 | 1/07/2017 - 30/06/2024 | n/a | n/a |
Related contract(s)
| Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|---|
| CAC541898 | Completed | Apr-17 | 70,000 | 27,200 |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Nation Wide | n/a | n/a | No mapping files provided |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 103234 | 0 | 0 | 0 |
Notes
20/11/2024 - This project was contracted in April 2017 and CAC541898 has now been completed.