Project summary
Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable |
---|---|---|---|---|---|
ERF101715 | Waste | Carbon Credits (Carbon Farming Initiative-Domestic, Commercial and Industrial Wastewater) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project is installing anaerobic digesters to replace deep open anaerobic lagoons that were treating industrial wastewater. The biogas that is generated from treatment of wastewater is collected by anaerobic digesters and is combusted using an internal combustion engine. | Combustion of biogas collected through anaerobic digesters | n/a |
Participants
Project Proponent | Agent | Significantly involved persons |
---|---|---|
SM Project Company Pty Ltd | n/a | n/a |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
9/10/2015 | 1/01/2017 - 31/12/2023 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC102337 | Lapsed/Terminated | Nov-15 | 100,000 | 46,881 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
New South Wales | 2580 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
39406 | 0 | 0 | 0 |
Notes
01/06/2017 Variation to participant name - from Quantum Power Limited to SM Project Company Pty Ltd
09/09/2024 (date of termination). This project was contracted in Nov-15 and CAC102337 has now been terminated.