EOP101244
Project Proponent Date Registered Method Type Method Description Notes
EDL (OCI) Pty Limited 24/07/2015 Industrial Fugitives Carbon Credits (Carbon Farming Initiative-Coal Mine Waste Gas) Methodology Determination 2015 (Compilation No. 3)
Read the methodology determination
This project is a displacement electricity production project that is installing and operating electricity production devices to capture and combust the methane component of coal mine waste gas from the mine. 20/02/2018 This project was contracted in Nov-15 and CAC102443 has now been completed. 26/09/2023 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Coal Mine Waste Gas) Methodology Determination 2015 (F2015L00162) to Carbon Credits (Carbon Farming Initiative - Coal Mine Waste Gas) Methodology Determination 2015 (F2021C01057).
Related contract(s)
Contract ID Status Auction date Original volume of abatement committed under contract Volume of abatement sold to the Commonwealth under contract
CAC102443 Completed Nov-15 26,576 26,576
Location
Project location Postcode Project Area(s) Mapping files
Queensland 4709 n/a No mapping files provided
Carbon Credit units
Total KACCUs issued Total KACCUs relinquished Total NKACCUs issued Total NKACCUs relinquished
577349 0 0 0

Unique key

EOP101244