Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| EOP101208 | Waste | Carbon Credits (Carbon Farming Initiative-Landfill Gas) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project installs a new landfill gas collection system to capture and combust gas generated at the landfill from legacy and non-legacy waste. | New project | n/a | Methane sent to a combustion device calculated using the quantity of landfill gas | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| LMS Energy Pty Ltd | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 26/05/2015 | 1/09/2016 - 31/08/2028 | n/a | n/a |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Queensland | 4817 | n/a | No mapping files provided |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 61331 | 0 | 0 | 0 |
Notes
21/09/2021 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2015L00059) to Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2021C00494).
28/06/2022. This project was contracted in Apr-17 and CAC668305 has now been completed.
28/06/2022. This project was contracted in Apr-17 and CAC668305 has now been completed.