Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
EOP101075 | Agriculture | Carbon Credits (Carbon Farming Initiative) (Destruction of Methane from Piggeries using Engineered Biodigesters) Methodology Determination 2013 (Compilation No. 1)
Read the methodology determination |
This project uses engineered biodigesters to collect and combust biogas from piggery manure. The engineered biodigesters were installed instead of anaerobic lagoons. |
Participants
Project Proponent |
---|
Charles I.F.E. Proprietary Limited |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
12/03/2015 | 1/01/2016 - 31/12/2022 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC102330 | Completed | Nov-15 | 35,000 | 35,000 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
Victoria | 3352 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
58496 | 0 | 0 | 0 |
Notes
08/09/2017 Variation of project method - from Carbon Credits (Carbon Farming Initiative) (Destruction of Methane from Piggeries using Engineered Biodigesters) Methodology Determination 2013 to Carbon Credits (Carbon Farming Initiative) (Destruction of Methane from Piggeries using Engineered Biodigesters c.1) Methodology Determination 2013.
06/12/2022 This project was contracted in Jan-16 and CAC102330 has now been completed.
06/12/2022 This project was contracted in Jan-16 and CAC102330 has now been completed.