Project summary
| Project ID | Method Type | Method | Description | Project activities | Project suppressors, if applicable | Estimation or measurement approach or model | Enforceable undertakings related to this project | Supplementary project information |
|---|---|---|---|---|---|---|---|---|
| EOP100772 | Savanna Fire Management | Carbon Credits (Carbon Farming Initiative-Emissions Abatement through Savanna Fire Management) Methodology Determination 2015
Read the methodology determination |
This project involves strategic and planned burning of savanna areas in the high rainfall zone during the early dry season to reduce the risk of late dry season wild fires. | Reducing fire emissions in the high rainfall area | n/a | n/a | n/a | n/a |
Participants
| Project Proponent | Agent |
|---|---|
| Indigenous Land and Sea Corporation | n/a |
Timings
| Registration | Crediting period | Permanence period | Model start date(s) |
|---|---|---|---|
| 18/09/2014 | 1/01/2015 - 31/12/2039 | n/a | n/a |
Related contract(s)
| Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|---|
| CAC102373 | Completed | Nov-15 | 95,000 | 95,000 |
Location
| Project location | Postcode | Project Area(s) | Mapping files |
|---|---|---|---|
| Queensland | 4871 | 819/SP181633 The project is in the Cook local government area. |
Project area mapping file (.kml) |
Australian carbon credit units
| Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
|---|---|---|---|
| 159899 | 0 | 0 | 0 |
Notes
08/09/2015 Variation of project method - from Carbon Credits (Carbon Farming Initiative) (Reduction of Greenhouse Gas Emissions through Early Dry Season Savanna Burning 1.1) Methodology Determination 2013 to Carbon Credits (Carbon Farming Initiative - Emissions Abatement through Savanna Fire Management) Methodology Determination 2015.
01/10/2015 Variation to participant name - from Indigenous Land and Sea Corporation to Indigenous Land and Sea Corporation and Corporate Carbon Solutions Pty Ltd.
05/05/2020 This project was contracted in Nov-15 and CAC102373 has now been completed.
12/12/2022 Variation to participant name - from Indigenous Land and Sea Corporation and Corporate Carbon Solutions to Indigenous Land and Sea Corporation.
01/10/2015 Variation to participant name - from Indigenous Land and Sea Corporation to Indigenous Land and Sea Corporation and Corporate Carbon Solutions Pty Ltd.
05/05/2020 This project was contracted in Nov-15 and CAC102373 has now been completed.
12/12/2022 Variation to participant name - from Indigenous Land and Sea Corporation and Corporate Carbon Solutions to Indigenous Land and Sea Corporation.