Project summary

Project ID Method Type Method Description
EOP100640 Waste Carbon Credits (Carbon Farming Initiative-Landfill Gas) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination
This project installs a new landfill gas collection system on or later 1 July 2010 to collect gas generated from waste that was accepted at the facility before 1 July 2012 (legacy waste) and combust the gas using a flare.

Participants

Project Proponent
Cairns Regional Council

Timings

Registration Crediting period Permanence period
11/02/2014 13/12/2014 - 12/12/2026 n/a

Related contract(s)

Contract ID Status Auction date Original volume of abatement committed under contract Volume of abatement sold to the Commonwealth under contract
CAC102466 Completed Apr-16 5,383 5,383

Location

Project location Postcode Project Area(s) Mapping files
Queensland 4870 n/a No mapping files provided

Australian carbon credit units

Total KACCUs issued Total KACCUs relinquished Total NKACCUs issued Total NKACCUs relinquished
67461 0 0 0

Notes

08/06/2016 This project was contracted in Apr-16 and CAC102466 has now been completed.

01/07/2022 Variation of project method - from Carbon Farming (Capture and Combustion of Methane in Landfill Gas from Legacy Waste) Methodology Determination 2012 (F2012L01688) to the Carbon Credits (Carbon Farming Initiative Landfill Gas) Methodology Determination 2015 (F2021C00494) .