Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
EOP100519 | Waste | Carbon Credits (Carbon Farming Initiative-Alternative Waste Treatment) Methodology Determination 2015
Read the methodology determination |
This project transitioned from a revoked ('CFI') method and continues to divert mixed solid waste from landfills to the waste treatment facility for processing using an enclosed composting technology to produce a combustible fuel substitute. |
Participants
Project Proponent |
---|
Port Macquarie Hastings Council |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
19/12/2013 | 13/12/2014 - 12/12/2021 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC176776 | Completed | Apr-16 | 110,300 | 78,000 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
New South Wales | 2441 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
123969 | 0 | 0 | 0 |
Notes
22/04/2015 Variation of method - from Carbon Credits (Carbon Farming Initiative) (Enclosed Mechanical Processing and Composting Alternative Waste Treatment) Methodology Determination 2013 to Carbon Credits (Carbon Farming Initiative - Alternative Waste Treatment) Methodology Determination 2015.
20/06/2023 This project was contracted in May-16 and CAC176776 has now been completed.
20/06/2023 This project was contracted in May-16 and CAC176776 has now been completed.