Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
EOP100250 | Waste | Carbon Credits (Carbon Farming Initiative-Electricity Generation from Landfill Gas) Methodology Determination 2021
Read the methodology determination |
This project transitioned from a revoked ('CFI') method and continues to capture and combust gas generated at the landfill from legacy and non-legacy waste. |
Participants
Project Proponent |
---|
LMS Energy Pty Ltd |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
14/08/2013 | 13/12/2014 - 12/12/2026 | n/a |
Related contract(s)
Contract ID | Status | Auction date | Original volume of abatement committed under contract | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|---|
CAC354956 | Completed | Apr-15 | 89,000 | 84,000 |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
Tasmania | 7004 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
184398 | 0 | 0 | 0 |
Notes
29/06/2015 Variation of project method - from the Carbon Farming (Capture and Combustion of Methane in Landfill Gas from Legacy Waste) Methodology Determination 2012 method to the Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015
19/08/2019 Variation to participant name - from AGL Energy Services Pty Limited to Sustainable Energy Infrastructure Pty Ltd as trustee for Sustainable Energy Infrastructure Trust.
11/02/2022 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2015L00059) to Carbon Credits (Carbon Farming Initiative - Electricity Generation from Landfill Gas) Methodology Determination 2021 (F2022L00049).
07/03/2022 Variation to participant name - from Sustainable Energy Infrastructure Pty Ltd as trustee for Sustainable Energy Infrastructure Trust to LMS Energy Pty Ltd.
27/02/2023 This project was contracted in Apr-15 and CAC354956 has now been completed
19/08/2019 Variation to participant name - from AGL Energy Services Pty Limited to Sustainable Energy Infrastructure Pty Ltd as trustee for Sustainable Energy Infrastructure Trust.
11/02/2022 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2015L00059) to Carbon Credits (Carbon Farming Initiative - Electricity Generation from Landfill Gas) Methodology Determination 2021 (F2022L00049).
07/03/2022 Variation to participant name - from Sustainable Energy Infrastructure Pty Ltd as trustee for Sustainable Energy Infrastructure Trust to LMS Energy Pty Ltd.
27/02/2023 This project was contracted in Apr-15 and CAC354956 has now been completed