Project summary
Project ID | Method Type | Method | Description |
---|---|---|---|
EOP100101 | Waste | Carbon Credits (Carbon Farming Initiative-Landfill Gas) Methodology Determination 2015 (Compilation No. 1)
Read the methodology determination |
This project transitioned from a revoked ('CFI') method and continues to capture and combust gas generated at the landfill from legacy and non-legacy waste. |
Participants
Project Proponent |
---|
LMS Energy Pty Ltd |
Timings
Registration | Crediting period | Permanence period |
---|---|---|
17/08/2012 | 13/12/2014 - 12/12/2026 | n/a |
Location
Project location | Postcode | Project Area(s) | Mapping files |
---|---|---|---|
Queensland | 4556 | n/a | No mapping files provided |
Australian carbon credit units
Total KACCUs issued | Total KACCUs relinquished | Total NKACCUs issued | Total NKACCUs relinquished |
---|---|---|---|
87411 | 0 | 0 | 0 |
Notes
06/03/2015 Variation of project method - from the Carbon Credits (Capture and Combustion of Methane in Landfill Gas from Legacy Waste) Methodology Determination 2012 to Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015.
21/09/2021 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2015L00059) to Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2021C00494).
28/10/2021 This project was contracted in Apr-15 and CAC164941 has now been completed.
21/09/2021 Variation of project method - from Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2015L00059) to Carbon Credits (Carbon Farming Initiative - Landfill Gas) Methodology Determination 2015 (F2021C00494).
28/10/2021 This project was contracted in Apr-15 and CAC164941 has now been completed.