Contract overview
Contractor Name | Auction | Status |
---|---|---|
LMS Energy Pty Ltd | Apr-22 | Active |
Contracted project(s)
- Swanbank Landfill Gas Upgrade Project (ERF167268)
Delivery data
Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|
Optional Delivery | 280,000 | 80,000 | 0 |
Contract timing
Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
---|---|---|---|---|---|
- | - | - | 7.00 years | No | 7.00 years |