Contract overview
Contractor NameTerra Carbon Pty Limited
AuctionJun-18
StatusActive
Contracted projects(s)
Project name Project ID
Darling River Eco Corridor #39
ERF121579
Delivery data
Created with Highcharts 11.4.8Remaining original volume of abatement commitedRemaining original volume of abatement commitedVolume of abatement sold to the Commonwealth under contractVolume of abatement sold to the Commonwealth under contractHighcharts.com
Delivery Obligation (indexed field)Fixed Delivery
Original volume of abatement committed under contract (indexed field)91,488
Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones0
Volume of abatement sold to the Commonwealth under contract29,472
Contract timing
Actual contract duration from commencement date-
Actual contract duration from contract date-
Actual contract end date-
Delivery period13.11 years
Subject to Conditions Precedent at time of contractYes
Total contract length, including time to fulfil Conditions Precedent14.04 years