Contract overview
Contractor Name | Auction | Status |
---|---|---|
NESLECOVE PTY LTD as the Trustee for CELI MANUFACTURING SUPER BENEFITS FUND | Sep-20 | Active |
Contracted project(s)
- Bundure Station Forest Regeneration Project (ERF159588)
Delivery data
Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|
Optional Delivery | 97,680 | 32,708 | 0 |
Contract timing
Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
---|---|---|---|---|---|
- | - | - | 9.99 years | No | 9.99 years |