Contract overview
| Contractor Name | Auction | Status |
|---|---|---|
| LMS Energy Pty Ltd | Dec-18 | Completed |
Contracted project(s)
- Southern Waste Landfill Gas Upgrade Project (ERF111111)
- Pedler Creek Landfill Gas Upgrade Project (ERF109627)
Delivery data
| Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|
| Fixed Delivery | 460,000 | 157,202 | 302,798 |
Permanent exit arrangement data
This information is provided for all eligible fixed delivery contracts, it should not be used to infer whether a particular seller has entered into, or intends to use, the permanent exit arrangement.
| Delivery volume outstanding as at 1 January 2025 | Volume delivered and sold since 1 January 2025 | Volume released under the Permanent Exit Arrangement | Eligibile for permanent exit arrangements |
|---|---|---|---|
| 45,000 | 11,250 | 33,750 | Yes - 25% or more of the volume that was outstanding as at 1 Jan 2025 has been delivered |
Contract timing
| Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
|---|---|---|---|---|---|
| 7.65 years | 7.66 years | 13/08/2026 | 7.65 years | No | 7.66 years |