Contract overview
| Contractor Name | Auction | Status |
|---|---|---|
| EDAH PASTORAL COMPANY PTY LIMITED | Dec-18 | Completed |
Contracted project(s)
- Edah Station Regeneration Project (ERF126394)
Delivery data
| Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|
| Fixed Delivery | 12,500 | 3,061 | 9,439 |
Permanent exit arrangement data
This information is provided for all eligible fixed delivery contracts, it should not be used to infer whether a particular seller has entered into, or intends to use, the permanent exit arrangement.
| Delivery volume outstanding as at 1 January 2025 | Volume delivered and sold since 1 January 2025 | Volume released under the Permanent Exit Arrangement | Eligibile for permanent exit arrangements |
|---|---|---|---|
| 0 | 0 | 0 | N/A |
Contract timing
| Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
|---|---|---|---|---|---|
| 3.91 years | 5.41 years | 13/05/2024 | 5.00 years | Yes | 6.49 years |