Contract overview
| Contractor Name | Auction | Status |
|---|---|---|
| EDL LFG (NSW) Pty Ltd; EDL LFG (VIC) Pty Ltd | Apr-15 | Completed |
Contracted project(s)
- Brooklyn Landfill Gas Project (EOP100099)
- Eastern Creek Landfill Gas Project (EOP100103)
- Jacks Gully Landfill Gas Project (EOP100059)
Delivery data
| Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|
| Fixed Delivery | 913,546 | 0 | 913,546 |
Contract timing
| Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
|---|---|---|---|---|---|
| 7.41 years | 7.41 years | 20/09/2022 | 7.48 years | No | 7.48 years |