Contract overview
Contractor Name Auction Status
Sustainable Energy Infrastructure Pty Ltd as trustee for Sustainable Energy Infrastructure Trust Apr-15 Completed
Contracted projects(s)
Project name Project ID
Glenorchy Landfill Gas Abatement Facility
EOP100247
Delivery Obligation (indexed field) Original volume of abatement committed under contract (indexed field) Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones Volume of abatement sold to the Commonwealth under contract
Fixed Delivery 179,000 12,000 167,000
Contract timing
Actual contract duration from commencement date Actual contract duration from contract date Actual contract end date Delivery period Subject to Conditions Precedent at time of contract Total contract length, including time to fulfil Conditions Precedent
7.84 years 7.84 years 27/02/2023 7.87 years No 7.87 years