Contract overview
Contractor Name | Auction | Status |
---|---|---|
DEWS PASTORAL HOLDINGS PTY LTD | Sep-20 | Lapsed/Terminated |
Contracted project(s)
- Yalbalgo Station Forest Regeneration Project (ERF158284)
Delivery data
Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|
Optional Delivery | 400,000 | 112,999 | 0 |
Contract timing
Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
---|---|---|---|---|---|
3.22 years | 3.22 years | 20/12/2023 | 9.99 years | No | 9.99 years |