Contract overview
| Contractor Name | Auction | Status |
|---|---|---|
| Robert Homewood | Dec-18 | Lapsed/Terminated |
Contracted project(s)
- Wondinong Station Regeneration Project (ERF123773)
Delivery data
| Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
|---|---|---|---|
| Fixed Delivery | 6,000 | 0 | 0 |
Contract timing
| Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
|---|---|---|---|---|---|
| 0.92 years | 3.11 years | 28/01/2022 | 1.99 years | Yes | 6.03 years |