Contract overview
Contractor Name | Auction | Status |
---|---|---|
AAK PUUL NGANTAM LTD. | Nov-15 | Completed |
Contracted projects(s)
Project name | Project ID |
---|---|
Savanna Burning Investment Ready Project - Cape York Pilot Aurukun |
EOP100972 |
Delivery Obligation (indexed field) | Original volume of abatement committed under contract (indexed field) | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|
Fixed Delivery | 60,000 | 0 | 60,000 |
Contract timing
Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
---|---|---|---|---|---|
4.54 years | 4.54 years | 28/05/2020 | 4.99 years | No | 4.99 years |