Contract overview
Contractor Name | Auction | Status |
---|---|---|
Adelaide Brighton Cement Limited | Nov-15 | Completed |
Contracted project(s)
- Birkenhead Additional Wood Firing Project (ERF101774)
Delivery data
Delivery Obligation | Original volume of abatement committed under contract | Volume released through Fixed Delivery exit arrangements or lapsed Optional Delivery milestones | Volume of abatement sold to the Commonwealth under contract |
---|---|---|---|
Fixed Delivery | 143,484 | 65,500 | 77,984 |
Contract timing
Actual contract duration from commencement date | Actual contract duration from contract date | Actual contract end date | Delivery period | Subject to Conditions Precedent at time of contract | Total contract length, including time to fulfil Conditions Precedent |
---|---|---|---|---|---|
7.05 years | 7.68 years | 18/07/2023 | 7.19 years | Yes | 7.82 years |